VALVIC offers design and detail engineering of electrical systems for modern industrial plants. It includes generation of single line diagrams, specifications for electrical switchgear and equipment, like transformers, motor control centers, starters, and more.
We are the ideal instrumentation and safety design partners for leading companies from diverse sectors to support plant upgrade or building newer installations. Our detail instrumentation engineering team helps implement the right instrumentation and safety systems to rectify possible challenges for both brown and greenfield projects.
So, whether you need a facility upgrade or a design for an upcoming facility, VALVIC experienced detail design engineering team is equipped with the required technical insight to help you seamlessly sift through the entire project journey.
Industry Codes and Standards adhered to by our Designers
AEA, IRAM, IECC, DIN, SRT900/15, ISA S5.1, NEC.
We can help you in…
- Power system studies including Arc Flash, OCPD Coordination, & Voltage Drop
- Power distribution equipment & systems specification & design
- Area classification plans & details
- Facility & equipment grounding
- Lighting studies & systems
- Full 3D modeling, orthographic, & detailed design packages
- Controls engineering & design
- Utility coordination
- PLC/DCS programming & panel layout
- Instrumentation loop diagrams & wiring schematics
- Motor, valve, ESD, VFD, & other control system schematics
- On-site construction support
- Procurement assistance
Electrical Shut Down , San Diego Plant
Customer: YPF SA
Location: Chubut – Argentina
The Service consisted on surveying existing electrical facilities in order to determine the consequences they could suffer in an eventual general shutdown, storage availability, and response times in case of an eventuality.
Rules, standards and regulations applied:
- Electrical Works: IEEE,IRAM, IEC, DIN, AEA 90365, ISA S5.1
Loop Contraste Agar– Tres Picos
Customer: Pan American Energy-BP
Location: Cuenca Golfo San Jorge – Tres Picos.
The Project consisted on executing detailed engineering for Crude Oil Storage Tanks including, civil, and piping works, as well as electrical and instrumentation works and erection procedures.
Rules, standards and regulations applied:
- ASME B31.3
- Cirsoc
- IEC, DIN, NEC
- ISA S5.1
Project:
Loop Contraste Agar